Oakville WPP Phase 2 Upgrades

Aerial overview of Water Purification Plant
Entrance into Water Purification Plant
Trench for Yard Pipe
Excavation for Manhole installation
stairway over process piping
Building with two overhead doors behind gated transformers and enclosure
pump and pipe gallery
Large concrete pipe penetrating foundation wall
filters
Project Type: 
Water Treatment
Project Owner: 
The Regional Municipality of Halton
Project Consultant: 
Associated Engineering
Project Value: 
$23,000,000
Project Years: 
2012-2014

Retrofit of an existing Water Purification Plant which includes upgraded treatment processes, modifications / additions to existing building structures, upgrades to electrical components and routing, installation of Reinforces Pressure Pipe and Concrete Pressure Pipe.