Terrace Bay WTP

Tower Crane and Formwork for Terrace Bay Water Treatment Plant
Project Type: 
Water Treatment
Project Owner: 
Township of Terrace Bay
Project Consultant: 
KGS Group
Project Years: 
2003-2004

Construction of the Terrace Bay Water Treatment Plant including; four conventional slow sand filters, two clearwell reservoirs, vertical turbine low & high lift pumping equipment, pressure filtration equipment, diesel generator, chemical equipment and piping, office and laboratory additions, power distribution equipment, and approximately 3km of HOPE yard piping systems, some of which was directionally drilled.