Annacis Island Wastewater Treatment Plant SCT Blower Replacement
The Annacis Island Wastewater Treatment Plant Blower Installation project included the removal of two existing solids contact tank blowers and associated items and the installation of three new 700hp blowers with three pad mounted transforms and associated items.
To complete the upgrade on the MCC/Switchgear to accommodate the three new blowers, a new soft starter for Blower 1 and a temporary Diesel Generator were required to be on standby for the emergency usage of Blower 1, which was an existing 800hp Blower.
Along with the blower upgrades, there was a CDAC upgrade that included new instrumentation, controls, a control panel, and termination panels. All work was coordinated around an operating facility to ensure no plant interruptions occurred.
NAC self performed all civil, mechanical and electrical works for this project.
Project Delivery Methods:
Project Sectors:
Project Services:
Project Owner:
- Metro Vancouver, BC
Project Consultant:
- Brown & Caldwell
Year of Completion:
2015Related Projects
-