Winnipeg South Wastewater Treatment Plant Expansion Phase IV

 Crane and Bucket Concreting for Bioreactors and Blower Building slab
Formwork and rebar installation for concrete wall pour
Craning in Formwork for concrete wall pour
Formwork installation for concrete wall pour
Craning in Formwork for concrete wall pour
Construction of two Secondary Clarifier concrete structures
Project Type: 
Water Treatment
Project Owner: 
City of Winnipeg, MB
Project Consultant: 
CH2M
Project Value: 
$39,000,000
Project Years: 
2016 - 2017

The Winnipeg South Wastewater Treatment Plant Phase IV Expansion includes the construction of the following scope of work:

• Construction of three Bioreactors and one Blower Building concrete structures
• Construction of two Secondary Clarifier concrete structures
• Supply and Installation of precast concrete piles for the Bioreactors and Blower Building
• Supply and Installation of a 2100mm diameter concrete pipe and concrete chambers
• Supply and Installation of piping embeds
• Supply and Installation of concrete encased piping
• Supply and Installation of aluminum grating, aluminum handrails, aluminum checkered
• plate, aluminum stairs
• Excavation to facilitate the construction of the Bioreactor concrete structure
• Excavation to facilitate the construction of the Secondary Clarifiers concrete structures
• Excavation and backfilling to facilitate the construction of the 2100mm diameter CPP
• Removal of shoring to facilitate construction of the Bioreactors and Secondary Clarifiers
• Water leak testing and backfill of the Bioreactors and Secondary Clarifiers Structures
• Site dewatering and ground water depressurization
• Miscellaneous site maintenance